Coal power encountered emergency brake 16 departments issued a message to the coal power industry strong control.
The core suggests that | is at risk of excess coal capacity, and a powerful storm is coming. Recently, the national development and reform commission, ministry of industry, 16 departments jointly issued by the bureau of energy on the propulsion of supply side against and dissolving the opinions of the coal and electricity overcapacity risk of structural reform ", to the coal industry to a wide range of selection, stopped and delayed.
Since 2014, the construction of coal power has been surging, and in a few years, there have been a lot of problems. Now facing to improve the efficiency of industry, the important task of maneuver for clean energy development with high pressure, coal, electric power enterprises obviously also need outside of coal, the diversity of again to find their own way.

The department has issued a joint statement to strictly control coal capacity.

"The message has been received before, and now that the policy has come down, the cooperation project will not have to go on." On August 7, sun, the head of a coal enterprise Marketing Department in the province, told reporters. The company has already surveyed nearly half a year of coal and electrical cooperation projects, because a document appears, could be completely blown away.

Recently, the national development and reform commission and other 16 departments jointly issued the opinions on promoting supply-side structural reform to prevent the risk of overcapacity in coal power production (hereinafter referred to as the "opinions"). The "opinions" put a brake on the sustainable growth of coal power by eliminating backward production capacity, handling illegal projects, and strictly controlling new production capacity.

"The scope of this control is very large. In addition to the planning projects, the projects under construction are also included." Mr Sun told reporters that the "opinions" was a continuation of the government's work report this year on the concept of coal power generation capacity. The state council has called for the elimination, suspension and construction of coal-fired power capacity of more than 50 million kw to prevent the risk of overcapacity in coal and electricity production, improve the efficiency of the coal power industry, and promote the development of clean energy. Is the principle of "before" cancel nuclear a batch of a batch, slow or postponed a number of ', existing long into the planning and approval of coal construction project under construction plan, but from the point of view of the file, the slow process is gone, replaced by a strong capacity to action." "Said Mr. Sun.

"Opinion", "much starker choices-and graver consequences-in" period, the country will stop to postpone coal production capacity of 150 million kilowatts, eliminate backward production capacity of 020 million kw or more, the implementation of the 420 million mw coal-fired ultra low emission transformation and energy-saving reform of 340 million kilowatts, flexible modification of 220 million kw. By 2020, China's coal power generation will be controlled within 1.1 billion kilowatts, and qualified coal-fired power units will complete ultra-low-emission transformation, and the average coal power consumption will be reduced to 310 grams per kilowatt hour.

A number of market participants told reporters that the biggest market concerns in the "opinions" were the three major tasks of eliminating backward production capacity, handling illegal projects and strictly controlling new capacity. With respect to backward production capacity, the state has proposed to eliminate and shut down the coal power units (including coal-fired power units) that fail to meet the requirements under the rule of law. For projects irregularities, the provinces will be comprehensive screening coal project planning and construction, to build before nuclear, illegal approval, batch start building does not conform to, shutdown and production procedures are not congruent illegal coal project, and according to the actual situation in accordance with the rules in accordance with the classification process.

The risk warning mechanism for coal power planning, launched last year, will act as a threshold in this case. "Opinion" is put forward, in the annual coal project planning and construction of risk early warning, early warning level for red and orange provinces, no new coal planning construction scale, is really necessary according to the new "first pass after building, such as capacity substitution" principle of eliminating backward coal production capacity accordingly.

According to the national energy bureau released in May this year on the release in 2020 coal planning and construction of risk early warning notice, hunan and hainan provinces are the only 2020 coal and electricity planning and construction of risk early warning result for the green, henan, jiangxi, anhui and hubei provinces orange, risk early warning level for the rest of the 24 provinces, autonomous regions and municipalities directly under the results of the risk early warning to red, what does this mean for the henan province also, by 2020, will almost no new coal project.

A coal enterprise personage cattle, says Mr Shutting down coal unit and a freeze on coal project, for a significant impact on related businesses, but it also reflected on the other hand, from coal production control has been the urgent moment, "has strong policy to control the".

Coal power construction expansion type surplus.

Behind the strict controls are the ever-expanding scale of coal power, and the hidden worries that come with it.

A provincial power producer told reporters that since the national development and reform commission (NDRC) has delegated the power of coal-fired power to the provincial level in 2014, the speed of coal power has exploded. Coal mining is forced to absorb the coal production capacity, and the profits are relatively high, and the investment enthusiasm of relevant enterprises is huge. In our province, for example, in 2016, the number of coal-fired power mw production in our province, at least 2014, more than twice, at the same time, there are many big energy companies new electricity integration project layout.

A set of data can also illustrate the enthusiasm of coal power construction. Released according to the China federation of power "in the first quarter of 2016 the country's electricity supply and demand analysis and forecast report shows that in the first quarter of 2016, China's thermal power new power 17.46 million kw, record in recent years, in the same period. This also allowed China's thermal power capacity to exceed 1 billion kilowatts, nearly the total installed capacity of the United States.

But at the same time, the power generation of thermal power has been continuously negative for many reasons. Figures show that in March of 2016, China's thermal power generating capacity fell 2.2% year on year, equipment utilization hours of 1006 hours (1054 hours) including coal, lower compared to the 108 hours, has 20 months year-on-year decline in a row, to the lowest level in nearly 10 years.

It is to see such a concern, since the second half of last year, relevant departments have begun to regulate the scale and speed of coal power construction. As in May last year, the national development and reform commission and national energy bureau jointly issued the notice on promoting the development of China's coal and orderly, in the division of the warning area at the same time, in 2012 and before include cancelled the plan did not approve of coal project, will roll into the corresponding local power balance in the future, to be combined with the power supply and demand situation and arrange gradually after 2018.

Zhuo qi-dong wang gen consulting analyst told reporters that such measures, to a certain extent, to suppress the momentum of the construction of the coal, but due to the large amount of base, even if the "delayed", will have a huge installed base, at the same time, some companies take a variety of ways to evade restrictions, make policy did not has a strong production capacity.

It said that in 2016, the number of coal use hours in China was only 4,164 hours, and the second year in a row was less than 4,500 hours. According to the industry, 5,500 hours is the baseline for the planning and design of coal-fired power units, and the number of hours is less than 5000 basic representative installed surplus, so the excess phenomenon has begun to be obvious.

According to the data, in the first half of this year, China's thermal power completed investment and new installed capacity, but the new installed capacity of thermal power was still up to 14.21 million kilowatts, of which 11.12 million kilowatts were produced in coal alone. By the end of June this year, the total installed capacity of 6,000 kilowatts and above in China had reached 1.06 billion kw, up 4.6% from the same period last year, with a control scale of 1.1 billion kilowatts in 2020 with only 0.4 gigawatts left.

Therefore, the use of strong means to control the scale of coal power construction is the state's importance to the development of the industry and the main means to resolve the overcapacity of coal power. Mr. Niu believes that the main indicators in the notice, which are basically the same as the 13th five-year plan for electric power, are particularly tough on specific measures. "With such a top-level control, it is believed that the production capacity implementation plan will be introduced at the project level soon, which will be a shock to coal and electric enterprises." "Said Mr. Niu.

Electricity market construction for coal power to find a new way out.

In fact, in the past year, whether to continue to build a fire power project has caused many discussions in the industry. Problems such as excessive power, worsening smog and environmental pressure are often pointed at the coal industry.

Last year, henan was not only the red alert area for power planning, but also included in the main range of slow nuclear and slow construction, according to people with power generation.

So why accelerate the project? A number of coal companies say that, although the crisis is expected to be excessive, there is no better option for companies.

"Coal mining is not the beginning of a year or two, but there is a lag in construction, plus overcapacity, and the need to rely on coal power to fuel the inventory of coal and to convert it in place," he said. The relevant person in charge of a large coal enterprises in the province, told reporters that actually regardless of the period of coal strength or power strong, coal power pool and electricity integration development, for both coal and electricity, is is the effective means to reduce cost and seek higher profits. Rising at the same time, although the proportion of new energy, but within a decade, thermal power is still the one of the most important link in China's energy structure, coal enterprises also hope that through make super net emissions from power plants, to release the capacity and operating pressure.

Such good expectations may be broken in this adjustment. The reporter understands that, according to the top-level layout, the coal power future in the energy system positioning, will be gradually from the electric power source to the power supply transformation. "In other words, coal will gradually shift from the main power supply to the non-main power supply. Even if electricity consumption continues to rise across the country, the growth of coal will be very slow. Energy analyst sun chenggang told reporters.

Meanwhile, the surge in coal prices since the first half of this year has led to a sharp rise in the cost of coal. A reporter from datang power learned that many power generation companies, including five power generation groups, have seen a sharp decline in profits. Although from July onwards, many provinces, including henan, have coal-fired power generating units feed-in tariff hike, benchmarking of henan increases 2.28 points per kilowatt-hour, become the biggest rise in province, but compared with coal prices have jumped in, also can alleviate the pressure of the part of the cost. "In addition, how to eliminate the following three million kilowatt units will also affect the efficiency and operating costs of the enterprise." "Said the person.

In the face of many bad news, how to mobilize the enthusiasm of coal power enterprises to control the production is the key to the implementation of the policy. To this end, "opinion" in strict control, issued a series of support policies.

16 departments is put forward, such as industry, to establish a perfect power market capacity, research through electricity subsidies, local financial subsidies and other support policies, to undertake the task load coal unit, the heating season to hold back pressure units give reasonable compensation. Again, such as in included in the shut down and does not participate in the coal unit of capacity to replace, can enjoy is no more than 5 years after the closure of the electricity power, and can obtain certain economic compensation by transfer of power generation right transaction.

"Opinion" also mentioned at the same time, to encourage and facilitate large power generation group restructuring integration, encourage coal, electric power and other industrial chain upstream and downstream enterprises exert industrial chain synergies, strengthen coal, electric power enterprises, long-term cooperation, stability of coal market price; We will support superior enterprises and major enterprises in integrating coal and electricity resources through asset restructuring, equity cooperation, asset replacement and free transfer.

Mr Sun believes that for coal enterprises, coal and electricity integration of the traditional digestive capacity, has been more and more bad, "opinion" is also given the coal and electric power enterprises new ways, or increase the speed of the "unity", by means of the power capacity of market construction, extending industrial chain diversity and deep processing, this will be the future of coal, electric power enterprise in production control on new choice.
China has invested 1.6 billion yuan to build natural gas power plants in tanghe.

On August 8, the people's government of tanghe county and China electric power international development co., LTD. (hereinafter referred to as "China electric power") signed the signing ceremony.

, federation of industry and commerce chairman, vice President of cppcc.in shirakawa presided over signing ceremony, the county committee and minister of united front addressed ren ping, riverside street office secretary Yang had just speak, the county party committee secretary vitaly lee, long county party member of DE pay, county bureau the eldest branch, light and other related leaders and chief representative of China power zhengzhou liu, chief financial officer, lupin attended the project signing ceremony.

China electric power was registered and successfully listed in Hong Kong in 1994. It is a window enterprise of overseas financing of the original power department, mainly engaged in the construction and operation of power supply projects, overseas investment and financing and capital operation. Currently, it is a wholly owned subsidiary of China power investment corporation, one of China's five largest power generation groups.

China electric power will develop and build natural gas distributed energy station and heat supply project in tanghe county, and provide heat, electricity and cold energy supply to the county industrial agglomeration area and central urban area. At the same time, in tanghe county invested in the construction of natural gas distributed cold and hot electricity for the project.

The project is divided into two phases: the first phase of the construction of a 2 x 60MW gas-fired generating set, with a total investment of about 800 million yuan; The second phase is to expand the 2 x 60MW gas generating unit, with a total of 4 60MW gas generating units, with a total investment of about 1.6 billion yuan. After the project is put into operation, the annual power supply of gas power station is about 500 million kilowatts, annual heating amount is about 1.5 million GJ, annual sales revenue is 300 million yuan, and annual tax revenue is about 22.5 million yuan.

In the first half of the year, the company shut down its coal-fired power plant, which will focus on hydropower.

On the night of August 8, sichuan energy (600674, SH) handed over the half-year report card. In the first half of this year, Mr Chuan's report card was unsatisfactory, with revenues and profits falling - revenue fell 30.55 per cent year-on-year and net profit fell 11.98 per cent.

On August 9, sichuan cast pale NingTao energy investor relations in the "daily economic news" reporter interview, said jia Yang power shut down earlier this year resulting in a decline in sales revenue, will focus on hydroelectric power, Yang electric power will be shut down permanently. She also said that the second quarter was in a dry period and had less water than a year earlier, leading to less hydropower than usual.

Revenue, net profit double drop.

On the evening of August 8, sichuan energy released a semi-annual report. The company realized its operating income of 352 million yuan from January to June of 2017, a year-on-year decline of 30.55%. Net profit was 1.23 billion yuan, down 11.98% year on year. The basic earnings per share were 0.28 yuan.

In response to the decline in revenue, the company said there are three main reasons: the first is the decline in sales revenue caused by the shutdown of jianyang power; Second, tian wan river company, tianpeng electricity consumption decreased year-on-year, sales revenue declined; Third, tian wan river company, tianpeng electric power average sales price decline.

The decline in the investment income of yalong river company, which is the main share of the company's shares, and the fall of the company's subsidiary, tian wan river company, resulted from a year-on-year decline in profits.

It is worth noting that Yang electric power company, tianwan river, day peng power of sichuan energy level division, in addition to the early Yang electric power production, reporters found that announcement in carding tianwan river first-half net profit down 20.21% from a year earlier; Tianpeng electric net profit in the first half of the year was down 33.43% from the same period last year. Sichuan power, another unit of sichuan investment energy, reported a 34.17 per cent year-on-year fall in net profits in the first half of the year.

It also means that among the five first-tier subsidiaries of sichuan investment energy, three of the four subsidiaries are down and one is out of production.

Hydropower will be concentrated.

In a statement, the energy company said that as coal prices rose too much, the company avoided a big loss at the start of the year. In the future, the company will focus on hydropower and clean energy as its main business and continue to take advantage of clean energy.

Light NingTao said first-half loss mainly Yang electric power production, and in the first half from a year earlier water less, cause predominantly hydropower tianwan river company and day peng electric capacity than in previous years.

But comb "daily economic news" reporter found that announcement day peng power, for example, in the first half of 2016 day peng electric power net profit up 198% from a year earlier, but fell 33.43% year-on-year in the first half of this year, if in accordance with the same period of last year is also the mutagenicity of logic, day peng power net profit growth is why difference so big?

Tianpeng power, a hydroelectric power company, has seen its net profit decline this year largely due to less water coming in, he told reporters. Last year, although also is faced with the problem of water, but water is better than this year, combined with the day peng power is a diversified development, "day peng electric power is not only to hydroelectric power, there will be other third industry, therefore, net income rose last year." She said.

In the second half of the year, the performance of the energy, talk about ningtao is optimistic. She said that with the coming of the flood season, the performance of its hydroelectric power unit could improve.

China can build gezhouba group to sign the general contract of balak hydropower station in Malaysia.

On August 2, to build its backbone enterprises in China gezhouba group and Malaysia for yue state energy company hydroelectric project signing ceremony held in kuching balak, marking the Chinese can build and gezhouba group get breakthrough in the field of energy cooperation in Malaysia, will be all the way "area" of energy construction, written a new chapter of china-malaysia friendship.

Malaysia for yue state deputy chief minister and infrastructure department, the ministry of communications minister datuk armagh ˙ in sundance James ˙ mahindra, sand bailing yue state energy company, the board chairman datuk amar ˙ hamish zimbabwean, Chinese consul general in kuching FuJiJun, as well as the relevant person in charge of the gezhouba group attended the signing ceremony.

The hydropower station is located in the southwestern part of the state, with a total installed capacity of 1285 mw. It adopts concrete face rockfill dam, with a height of 188 meters and a normal water level of 220 meters, with a capacity of 29.9 billion cubic meters. The project fund is funded by the owner, and the project is scheduled to start in August 2017. The hydropower station is an important part of the plan of "the renewable energy corridor (SCORE)" in the state of sand fishing. It is also one of the largest infrastructure projects in the state. When the project is fully put into operation, it will add 1285 megawatts of renewable energy to Malaysia and provide sufficient electricity for local economic and social development. Project construction boom will provide about 3500 jobs for the local, at the same time cultivating a large number of skilled technical personnel, good management of high-quality electricity, provide talent support for local economic and social development, greatly boost local economic development and improving people's livelihood, for sustainable growth and the sand out of yue state, Malaysia's economic development to provide a steady stream of power.

Gezhouba group said that the One Belt And One Road initiative is a great idea to benefit the whole world and provides a broader development space for countries along the line of One Belt And One Road to deepen practical cooperation. The signing of the balak hydropower project is of great significance to improving the economic and trade cooperation between the two countries and deepening the friendly cooperation between the two countries and promoting the healthy development of the regional economy. Gezhouba group will further practice of the concept of sustainable development, and always adhering to the "fairness, integrity, win-win" philosophy of cooperation, actively promote the localization operation strategy, insist on compliance management according to law, pay attention to ecological sustainable development, always working to improve people's lives, promoting social development. Gezhouba group is willing to make full use of professional and technical advantages and international large engineering project construction management experience, to build balak hydropower projects into bilateral economic and trade cooperation model of innovation and development, promote the horse comprehensive strategic partnership to a new level.

10 ministries and commissions, such as shandong provincial development and reform commission and sasac, jointly issued coal control orders: priority arrangement of new energy sources such as landscape in planning, etc. (with notice)

Shandong province development and reform commission (NDRC) recently released about print and distribute "in 2017 in shandong province coal consumption reduction alternative work action plan of the notice, notify by shandong province development and reform commission, shandong via letter committee, shandong sasac 10 ministries and commissions such as shandong, shandong department of environmental protection, price bureau jointly issued.

The circular noted that efforts should be made to reduce the generation of inefficient coal-fired power plants. According to the energy development plan and the annual plan, the new energy generating capacity of shandong province will be about 3 million kilowatts in 2017, with the addition of 10.2 billion KWH. According to shandong electric into the "lu" and new energy development, optimizes the power plan, the maximum increase the utilization level of efficient environmental protection units at the same time, priority arrangement planning in new energy sources such as wind power and solar energy power generation planning, given calls from outside the province actively, strive to reduce inefficient coal unit power generation plan, try to reduce the coal consumption of 5.2 million tons. The following is the text of the notice:
Notice on the issuance of the plan of action on the replacement of coal consumption in 2017 in shandong province.

Rufa reform (2017) 857.

Municipal people's governments, provincial government departments:

According to the provincial party committee and government, the 2017 environmental protection outstanding problem crucial improvement plan, in order to further implement the key areas of coal consumption reduction alternative management interim measures "(change of ring hair [2014] no. 2984) and reducing the coal consumption of shandong province substitute work plan (LuFa change of ring [2015] no. 791), to ensure complete province national" by the end of 2017, 2012 tons of coal consumption less than in 2012 "the goal of the task, the provincial development and reform committee and the provincial government related departments to study and formulate the reducing the coal consumption in 2017 in shandong province alternative work action plan, hereby printed and distributed to you. Please combine this area, this department actual, serious organization implement.

Annex: the action plan for the reduction of coal consumption in 2017 in shandong province.

Shandong province development and reform commission shandong economic and information commission.

Shandong provincial department of housing and urban-rural development.

Shandong provincial environmental protection bureau of shandong province.

Shandong provincial bureau of quality and technical supervision.

Shandong province coal industry bureau shandong price bureau.

July 24, 2017.

The attachment

In 2017, coal consumption in shandong province will be replaced by coal consumption.

Work action plan

According to the provincial party committee and government, the problems of environmental protection in 2017 comprehensive improvement of crucial plan about work to reduce coal consumption, combined with reducing the coal consumption of shandong province substitute work plan to determine the division of tasks, in order to complete our province national "by the end of 2017, 2012 tons of coal consumption less than in 2012" the goal of the task, now will accelerate the coal consumption reduce work, in-depth implementation of various measures, coal made the following action plan.
I. work objective.

(a) through the implementation of the key industries, key enterprises, reduce the coal consumption, the year the province's net, reduce the coal consumption more than 27.06 million tons, the province's coal consumption in 2017 total amount control within 382.33 million tons.

(2) according to various cities in 2016, coal consumption statistics in zibo, zaozhuang, jining, Texas and other four preliminary coal consumption reduce task, to keep the coal consumption of negative growth; For jinan, Qingdao, dongying, yantai, weifang, taian, weihai, rizhao, laiwu, linyi, liaocheng, binzhou, heze, such as 13 cities, to clear objectives, the implementation of the measures, increasing aggregate complete net for reduce the coal consumption of 33.56 million tons (appendix 1).

Ii. Key tasks.

On coal consumption of key industries, key enterprises in our province, according to the country and eliminating capacity, backward production capacity, clear violations projects work deployment, strict standard and the time limit, take strong advance measures and reduce the coal consumption of the actual effect as soon as possible.

(I) complete the production capacity task of the steel industry as soon as possible. In 2017, the whole province plans to reduce the production capacity of crude steel by 5.27 million tons and the capacity of pig iron by 1.75 million tons. Among them: the production capacity of weifang is 2.2 million tons of crude steel, and 550,000 tons of iron production capacity is reduced. Laiwu steel production capacity of 1.24 million tons; Binzhou city reduces crude steel production capacity of 1.83 million tons; Linyi can reduce the iron production capacity by 1.2 million tons (annex 2). As of now, the production capacity of jinan has been shut down, and the production capacity of 1.2m tons of raw iron in linyi has been shut down. Other enterprises, crude steel and pig iron capacity, should make plans and clear responsibilities, and strive to complete the shutdown by the end of September. According to the closing time, compared with the production situation last year and this year, the actual effect of reducing coal consumption was calculated, and the coal consumption was reduced by 5.7 million tons.

(2) shut down outdated coal-fired power units as soon as possible. According to "speed up eliminating backward production capacity of coal industry of the action plan (LuFa change energy [2016] no. 1160), to have been included in the 2017 and shut down before but not yet closed (attachment 3), 1.6665 million mw unit have to stop running before the end of August. The relevant municipal people's government shall clarify the responsible departments and the responsible persons, formulate work plans with relevant enterprises, ensure the scheduled closure, and complete the demolition and acceptance before the end of the year. We will reduce coal consumption by 1.8 million tons by eliminating outdated coal-fired power units.

(iii) close the elimination of small coal-fired boilers as soon as possible. By the end of October 2017, seven transmission channel cities will completely eliminate the coal-fired boilers in the administrative region, totaling 15704 units and 15766 steamed tons per hour (annex 4). Among them, jinan city completely eliminated 35 steam tons/hour and the following coal-fired boilers in the administrative area, as well as the large stove and the operating small coal stove; Zibo, liaocheng 2 city to eliminate the administrative area of 20 evaporation tons per hour or less coal-fired boilers; Jining, Texas, binzhou, heze 4 city completely eliminated 10 steam tons/hour coal-fired boilers in the administrative region. 10 other cities, weifang, taian and laiwu 3, basically eliminated 10 steam tons/hour and the following coal-fired boilers in the administrative region; The remaining seven cities completely eliminated the construction area and the county town 10 steam tons/hour and the following coal-fired boilers. By closing down the coal-fired boilers, the coal consumption will be reduced by 4.5 million tons.

(4) to promptly complete the cleaning up of electrolytic aluminum illegal projects. According to enterprise self checking and verification in our province, our province the weiqiao pioneering group and xinfa group 2 companies comply with electrolytic aluminium production capacity of 3.21 million tons (attachment 5), and illegal coal unit supporting construction, large in coal consumption. Among them: weiqiao startup group has set up 5 electrolytic aluminum projects, with an illegal capacity of 2.68 million tons. The company has an illegal production capacity of 530,000 tons. By the above violations electrolytic aluminum projects, binzhou, liaocheng city people's government shall be responsible for shutting down before the end of July, at the same time, respectively to halt the corresponding scale coal unit (excluding have been incorporated into was eliminated and the previous year in 2017 shut down the unit). Among them, binzhou weiqiao group suspended coal power unit 5.7 million kw; Liaocheng xinfa group suspended coal power plant about 1 million kilowatts. According to the above violations, electrolytic aluminium production capacity and supporting coal unit shut down time, compared to last year and this year's production situation, specific accounting reduce the coal consumption of the actual effect, to reduce the coal consumption of 10 million tons.

(5) accelerate the winter clean heating project. Before November 15, 2017, the seven transmission channel cities will complete the gas generation or electric generation coal projects of more than 50,000 households in accordance with the principle of appropriate gas and electricity. Cities before the end of July in 2017 to develop aerobic coal or coal or electricity generation work implementation scheme in detail, completed before the end of September in households heating facilities construction and renovation project, November 15 complete commissioning and completion inspection and acceptance work. According to the actual completion of the winter cleaning and heating project of gas generation coal or electricity generation coal in each city, the actual effect of reducing coal consumption is calculated, and the coal consumption is reduced by one million tons.

(vi) efforts to reduce the generation plan of inefficient coal-fired power plants. According to the energy development plan and the annual plan, the province will increase the number of incoming calls in 2017 to 10.2 billion KWH, which will replace 4.5 million tons of coal consumption. The new energy generating capacity will be about 3 million kilowatts, replacing coal consumption by 700,000 tons. According to our province "announced in lu" and "new energy development, optimizes the power plan, maximize efficient environmental protection units in the use of level at the same time, priority arrangement planning in new energy sources such as wind power and solar energy power generation planning, given calls from outside the province actively, strive to reduce inefficient coal unit power generation plan, try to reduce the coal consumption of 5.2 million tons.

(7) focus on promoting winter peak production. We will strictly implement the production and control measures in the heating season, and we will carry out the task of performing the wrong peak production to enterprises and production lines. All the cement production lines in the province, including the production line of cement production with carbide slag, are all made in the wrong peak production. Among them, bear the residents heating, collaborative disposal of municipal waste and hazardous waste, such as the task of ensuring people's well-being production line can not wrong peak production in principle, but on the task of according to the maximum allowable load of check and ratify; Seven transmission channel city fault peak range contains powder grinding station, and 10 other cities do not contain powder mill station. Standards of alumina, electrolytic aluminum, carbon and other industries to leak more than 30%, 30%, 30% respectively over (in line), short of corresponding emission standard or limit the implementation of the production. The municipal people's government of the seven transport channels shall, before the end of September, submit the list of the production line of the production line of the wrong peak production line to the provincial economic and informatization commission and the environmental protection bureau for the record, and to the public. Through key industries to implement the wrong peak production or stop production measures to reduce coal consumption by 1 million tons.

Safeguard measures.

(I) clear division of labor. For the above seven key tasks, the division of responsibilities shall be carried out, and the relevant departments shall clarify the responsibilities and responsibilities, make plans and follow up the implementation. The provincial development and reform commission will focus on shutting down and eliminating outdated coal-fired power units and electrolytic aluminum illegal projects, and promoting the development of "external power" and new energy sources. The provincial economic and information technology commission will focus on the steel industry to reduce the production capacity, reduce the power generation plan of inefficient coal-fired power plants, and reduce the power generation of new energy sources in the province. The ministry of housing and urban-rural development will focus on cleaning and heating during the winter. The provincial environmental protection office will focus on shutting down the small coal-fired boilers. The provincial economic and information commission and the department of environmental protection jointly supervise the implementation of peak production in key industries.

(2) implementation of responsibilities. Municipal people's government, in particular, 13 have a net coal consumption reduce the task of the municipal people's government, want to combine all the key tasks within its own administrative region, make work plan, will net coal consumption reduce task decomposition, into various counties (city, area) and key coal consumption enterprises. At the same time, we must strengthen the leadership, is mainly responsible for comrades personally stresses, comrade in charge is responsible for depend on grasp, urged the county (city, area) people's government and key coal consumption detailed work plan of the enterprise, establish working parameter, the listed time limit responsibility list, measures list, list, from solid propulsion promptly implement strictly.

(3) strengthen supervision. Provincial coal consumption reduction substitute work coordination group to strengthen supervision and inspection, establish and improve the schedule, inspection, supervision, notification system. Control the list of responsibilities of various departments, list of measures, time limit list, strengthen daily schedule, and implement weekly summary and monthly bulletin on the progress of work. We should strengthen on-site inspection and timely release the notice of rectification, and timely take some responsible person and other methods to supervise the work.

Xinjiang's wind power and solar power capacity are among the highest in the country.

In the first half of this year, the electricity consumption of clean energy and photovoltaic power generation in the autonomous region was effectively used. On August 6, the reporter from the regional development and reform commission of the autonomous region, the country's wind power generation and solar power capacity in the forefront of the country.

By the end of June this year, the total installed capacity of wind power in xinjiang was 1835.40 mw, accounting for 22.9% of the total installed capacity, and second only to Inner Mongolia.

As of June this year, the total solar power generation capacity of the whole xinjiang was 9076,000 kw, accounting for 11.4% of the total installed capacity, ranking first in the country.

Influenced by multiple factors, the phenomenon of abandoned wind and light abandoning has become increasingly prominent in the second half of 2015. This has aroused the high attention of the party committee and the government of the autonomous region, seeking to expand the new energy consumption, and the work plan of "electrifying xinjiang" to solve the problem of abandoning wind and light.

According to the data, in the first half of this year, the total abandoned wind power was 7.25 billion kilowatt-hours, while the wind abandoning rate was 32.1%, down 11.8% year on year. When the total amount of power was abandoned, the rate of light rejection was 25.7%, a year-on-year decrease of 6.1 percentage points.

It is understood that the autonomous region is supporting the use of photovoltaic power generation to solve the problem of electricity and electricity shortage in remote areas, and combine photovoltaic development with poverty alleviation.